Cold Storage Facilities · Project Reference
Super-Long Span Post-Tensioned Cold Storage Project: Taiku Solution Reduces Overall Cost by 15%
Increased storage capacity by over 15%, reduced overall construction cost by 15%, shortened project duration, minimized cracking, and improved structural durability.
Project Overview
- Location
- Xiashan District, Zhanjiang City
- Scenario
- Cold Storage Facilities
- Client
- Tianhe (South China) Agricultural Materials Reserve and Logistics Base
- Designer
- Huashang International Engineering Co., Ltd.
- BICP Role
- Provided preliminary scheme consultation, technical review, detailed design, and professional engineering services
- Key Conditions
- Located in Xiashan District, Zhanjiang City, with a total building area of 79,500 m². The 1# cold storage is a 3-story structure with a building height of 23.9 m, utilizing bonded post-tensioned flat slab technology. The storage area measures 53 m × 116 m with column grids of 10.6 m × 11.4 m.
Project Challenges
The client prioritized maximizing storage capacity, eliminating expansion joints in the super-long structure, controlling early-age and long-term cracking, and shortening the construction schedule.
Proposed Solution
Adopted a large column grid of 11.4 m × 10.6 m with a post-tensioned flat slab system, increasing storage capacity by over 15%. The super-long storage area (116 m × 53 m) required only one post-cast strip instead of multiple expansion joints. Staged post-tensioning was implemented to mitigate early-age shrinkage cracks, while the pre-compression stress controlled deflection and cracking, enhancing structural durability.
Technical Implementation
The Tianhe (South China) Agricultural Materials Reserve and Logistics Base 1# Cold Storage is a representative case of BICP's Taiku product, completed between September and November 2021. The project is located in Xiashan District, Zhanjiang, with a total building area of 79,500 m², aiming to create a highly integrated agricultural supply chain hub. The 1# cold storage is a 3-story structure (height 23.9 m) using bonded post-tensioned flat slab technology, with plan dimensions of 53 m × 116 m and column grids of 10.6 m × 11.4 m.
Project Challenges:
- Storage Capacity: Zhanjiang, a major agricultural production city in Guangdong, demanded high storage capacity.
- Super-Long Structure: The 116 m long storage area exceeded the typical 50 m expansion joint limit for cast-in-place shear wall structures, which would have required multiple joints and delayed the year-end completion.
- Early-Age Cracking: High construction temperatures in the southern region increased the risk of early shrinkage cracks.
- Long-Term Cracking: Potential for floor cracking over time.
Solution and Advantages:
- Large Column Grid: The 11.4 m × 10.6 m post-tensioned flat slab design increased storage capacity by over 15%. The smooth soffit facilitated polyurethane insulation spraying, contributing to a 15% reduction in overall cost.
- Elimination of Expansion Joints: The super-long storage area (116 m × 53 m) required only one post-cast strip, significantly shortening the construction schedule.
- Crack Control: Staged post-tensioning applied pre-compression to reduce early shrinkage cracks.
- Durability: Pre-compression minimized temperature-induced stresses, controlling deflection and cracking for improved long-term durability.
BICP, as a full-process solution provider for post-tensioned low-carbon construction, has over 13 years of experience in the field. We are committed to advancing low-carbon and digital construction for high-quality structural development.
Delivered Value
Increased storage capacity by over 15%, reduced overall construction cost by 15%, shortened project duration, minimized cracking, and improved structural durability.