Cold Storage Facilities · Project Reference

Xinrongmao Cold Chain Project

Back to Home
01

Project Overview

Location
Shenzhen, Guangdong Province, China
Scenario
Cold Storage Facilities
Client
Xinrongmao Group Co., Ltd.
General Contractor
China Construction Second Engineering Bureau Co., Ltd.
Designer
Huashang International Engineering Co., Ltd.
BICP Role
Post-tensioned structural design and technical service
Key Conditions
Xinrongmao Group is a major importer of fresh fruit in China, with a supply chain covering the world's main fruit-producing regions. As the imported fruit market keeps growing, the company needs more than storage capacity: its cold storage must also support a fully automated storage and retrieval system (AS/RS) for end-to-end automated cold storage of fruit and vegetables. This is a newly built cold storage facility using a post-tensioned wide shallow beam structural system. Two requirements shaped the structural scheme: floor loads from stacked goods and racking are heavy and concentrated, so the punching shear margin at flat-slab column heads had to be carefully controlled; and the AS/RS places high demands on the precise match between the column grid and the racking, on slab load capacity and on deflection control. BICP was responsible for the post-tensioned structural design and technical services, proposed the post-tensioned wide shallow beam scheme, and carried out BIM coordination with the racking design, delivering an integrated structure-and-racking solution.
02

Project Challenges

Structural safety under heavy loads. Flat slabs are widely used in cold storage because they are simple to build and make good use of clear height, but their weak point is punching shear at the column heads. When floor loads (such as heavy stacking or concentrated racking loads) exceed the design limits, the slab around the column head can fail in shear, and this failure mode tends to be sudden and dangerous, so punching shear safety must be carefully controlled in heavily loaded cold storage.
Special requirements of the automated racking system. The AS/RS racking is tall with concentrated loads, and the column grid must match the racking rails precisely. Structural design had to proceed together with the racking layout rather than treating slab design separately, as in a conventional cold store.
Storey height and clear-height control. While ensuring structural safety, beam depth had to be kept low to avoid taking up clear height, which is essential for the automated racking to operate effectively.

03

Proposed Solution

Wide shallow beam scheme: wide, shallow beams are set within the floor to carry loads between columns in bending, avoiding the punching shear failure mode of flat slabs and making the design easier to pass structural review. Being shallow keeps beam depth low so it takes little clear height; being wide provides enough bending section to carry the loads at a small depth.
Post-tensioned wide shallow beams: post-tensioning tendons in the beams apply a moment that counteracts the load moment, raising section capacity without increasing beam depth and improving crack resistance. Compared with a conventional beam-and-slab frame, the storey height is reduced by about 500mm.
BIM coordination with the racking system: from the structural design stage, BICP coordinated with the racking supplier through BIM analysis so that the column grid matched the racking layout and the concentrated rail loads fell at suitable positions on the beams, avoiding rework and design changes caused by mismatches between racking installation and structural provisions.
Post-tensioning was carried out under a dedicated construction method statement: the wide shallow beams were stressed once the concrete reached the specified strength age, and stressing data were recorded span by span to confirm that the tendon forces matched the design values.
Coordination with the racking supplier continued throughout the project, with the BIM model kept up to date so that the column grid, beam positions and racking layout matched precisely on the construction drawings, effectively controlling the risk of design changes during installation.

04

Project Background


05

Technical Challenges


06

Solution

Wide shallow beam scheme: wide, shallow beams are set within the floor to carry loads between columns in bending, avoiding the punching shear failure mode of flat slabs and making the design easier to pass structural review. Being shallow keeps beam depth low so it takes little clear height; being wide provides enough bending section to carry the loads at a small depth.

Post-tensioned wide shallow beams: post-tensioning tendons in the beams apply a moment that counteracts the load moment, raising section capacity without increasing beam depth and improving crack resistance. Compared with a conventional beam-and-slab frame, the storey height is reduced by about 500mm.

BIM coordination with the racking system: from the structural design stage, BICP coordinated with the racking supplier through BIM analysis so that the column grid matched the racking layout and the concentrated rail loads fell at suitable positions on the beams, avoiding rework and design changes caused by mismatches between racking installation and structural provisions.


07

Implementation

Post-tensioning was carried out under a dedicated construction method statement: the wide shallow beams were stressed once the concrete reached the specified strength age, and stressing data were recorded span by span to confirm that the tendon forces matched the design values.

Coordination with the racking supplier continued throughout the project, with the BIM model kept up to date so that the column grid, beam positions and racking layout matched precisely on the construction drawings, effectively controlling the risk of design changes during installation.


08

Delivered Value

On completion, the post-tensioned wide shallow beam scheme met the structural safety requirements for heavy loads while providing the structural space the automated racking system needed. Racking installation proceeded according to the coordinated design, with no rework caused by conflicts between the structure and the racking layout.

Compared with a conventional beam-and-slab frame, the storey height was reduced by about 500mm; compared with a flat slab, punching shear risk at the column heads is easier to control and structural safety is higher. The design passed structural review and removed the owner's concerns about structural safety.


09

Reference Value

The project offers a reference for newly built cold storage with heavy floor loads and high clear-height requirements, balancing structural safety and clear height. The post-tensioned wide shallow beam scheme suits cold chain projects where floor loads are heavy, the punching shear margin of a flat slab is insufficient and clear height matters, as well as smart cold storage that must match automated racking precisely.

10

Delivered Value

On completion, the post-tensioned wide shallow beam scheme met the structural safety requirements for heavy loads while providing the structural space the automated racking system needed. Racking installation proceeded according to the coordinated design, with no rework caused by conflicts between the structure and the racking layout.
Compared with a conventional beam-and-slab frame, the storey height was reduced by about 500mm; compared with a flat slab, punching shear risk at the column heads is easier to control and structural safety is higher. The design passed structural review and removed the owner's concerns about structural safety.
The project offers a reference for newly built cold storage with heavy floor loads and high clear-height requirements, balancing structural safety and clear height. The post-tensioned wide shallow beam scheme suits cold chain projects where floor loads are heavy, the punching shear margin of a flat slab is insufficient and clear height matters, as well as smart cold storage that must match automated racking precisely.